Energy & Infrastructure
Key points of the quarter
-
In Mali, a diesel shortage and a network incident are worsening the electricity crisis in Bamako.Fuel supplies to Bamako, severely disrupted by the JNIM blockade of several corridors since 2025, had improved starting in December thanks to the resumption of escorted convoys. However, in early March 2026, the diesel shortage worsened again, and available volumes were primarily directed to Énergie du Mali (EDM) and its thermal power plants. This deterioration compounded the consequences of a fire that occurred on the night of February 23-24 at the SEMAF substation in Sébénicoro, which had already affected Bamako's power grid. By mid-March, some neighborhoods were reporting more than 24 consecutive hours without electricity, while others were receiving only about three to seven hours of power per day, far short of the target of approximately 19 hours announced before Ramadan.1Why it's important: The crisis highlights two distinct vulnerabilities: the dependence of a significant portion of electricity production on imported fuels and the fragility of the transmission and distribution network. As a historical benchmark, a UNDP study estimated that in 2020, Mali's electricity production came from approximately 69% thermal power, 26,8% hydroelectric power, and 4,2% solar power. This figure should be interpreted as a dated reference point, not as an estimate of the energy mix in 2026.
-
In Senegal, Sangomar maintains high uptakes, GTA exceeds its nominal capacity, and domestic gas-to-power is progressing.Official reports from the Senegalese Ministry of Energy indicate that four Sangomar cargoes, representing approximately 3,8 million barrels, were marketed in January 2026; volumes loaded remained high in February and March, with approximately 2,98 million barrels marketed in March. These figures correspond to the volumes loaded or marketed and should not be confused with the field's monthly production. On GTA, Kosmos Energy reported that in the first quarter of 2026, gross production was growing at an annualized rate equivalent to approximately 2,85 million tonnes of LNG, above the nominal capacity of 2,7 Mtpa, with 9,5 gross cargoes shipped during the quarter. In parallel, an onshore power plant is under construction near Saint-Louis/Gandon, and the partners anticipated the start of construction of the gas pipeline connection around mid-2026. The “Phase 1+” project also targets the domestic markets of Senegal and Mauritania.2Why it's important: The quarter confirms the increasing export of Senegalese hydrocarbons, but the next strategic challenge is domestic: converting some of this new gas resource into electricity that is actually available on the grid. The public objective mentioned in 2025 of eventually directing a portion of GTA's production towards the domestic market remains a deployment goal, not a result already achieved by Q1 2026.
-
Guinea puts the Fomi dam project back on the agenda with its Chinese partnersOn January 14, 2026, the Guinean government held a strategic meeting with the Chinese ambassador in Conakry and several Guinean officials regarding the revival of the Fomi multi-purpose dam on the Niandan River. On February 20, the Ministry of Planning presented this meeting as a step towards moving from discussions to implementation, within the framework of Sino-Guinean cooperation. The historic project is generally sized around 90 MW and also includes a significant irrigation component with downstream impacts in Mali, particularly for the Office du Niger irrigation scheme. At the time of publication, however, these announcements did not constitute proof of finalized financing or the actual commencement of construction.3Why it's important: Fomi remains a regional project encompassing energy, agriculture, and water resources. The period from January to February 2026 marks a political and technical resumption of the project, but the decisive signal will be the transition to verifiable financial and contractual commitments, followed by the physical execution of the works.
Overview of the sector
The first quarter of 2026 illustrates three very different trajectories within the energy sector in Francophone sub-Saharan Africa. In Mali, the electricity crisis in March resulted from a combination of constraints: a diesel shortage in a deteriorating security context and a fragile grid following the fire at the SEMAF substation in Sébénicoro. In Senegal, the Sangomar and GTA dams continued their ramp-up, while projects aimed at converting some offshore gas into domestic electricity progressed but are not yet operational. In Guinea, the Fomi dam project was put back on the political agenda with China, but the sequence observed in Q1 still corresponds to a relaunch of the project, and not to the confirmation of final financing or the actual restart of construction.
At the time of publication, consistent national statistics specifically covering the first quarter of 2026—electricity production, transmission and distribution losses, electrification rates, or generation mix—were not available for most of the countries covered. The figures presented in this note are therefore limited to data that can be traced back to identifiable sources: official Senegalese hydrocarbon reports, central bank announcements, explicitly dated historical data, and verified information on projects and incidents during the quarter.
A consolidated set of comparable electricity indicators for the whole of Francophone sub-Saharan Africa could not be established for Q1 2026. Therefore, unverifiable or non-comparable indicators are intentionally omitted rather than estimated. Guinea, which uses the Guinean franc and has its own central bank, is also outside the BCEAO and BEAC frameworks presented in Section III.
Monetary-zone dynamics (CFA franc countries)
Mali and Senegal, analyzed in Sections I and IV, are both members of the UEMOA. The UEMOA data presented in this section therefore apply to these two countries. Guinea, also covered by this note, does not belong to the CFA franc zone and is not included in this section. See the note on data availability above.
WAEMU Zone
At its meeting on March 4, 2026, the BCEAO lowered its main policy rate by 25 basis points to 3,00% and the marginal lending facility rate to 5,00%, effective March 16. The required reserve ratio remained unchanged at 3,00%. This decision came against a backdrop of continued disinflation: inflation for the fourth quarter of 2025 was reported at -0,8%, while inflation for the whole of 2025 remained virtually zero. At this meeting, the BCEAO anticipated a slight rebound in inflation to around 1,4% in 2026. Growth in the Union in 2025 was estimated at 6,7%, compared to 6,2% in 2024, and the BCEAO projected growth of 6,4% in 2026.4
CEMAC zone
No events specific to the CEMAC region are covered in the first quarter 2026 report. The BEAC's key interest rate remained at 4,75%, and the marginal lending facility rate at 6,25%, throughout the quarter. These levels were set following a 25 basis point increase at the meeting of December 15, 2025. The BEAC did not hold an ordinary session of its Monetary Policy Committee during the first quarter and confirmed the maintenance of these rates at its meeting of April 2, 2026.4
| Indicator | UEMOA | CEMAC |
|---|---|---|
| Central bank key interest rate (end of quarter) | 3,00% | 4,75% |
| Marginal lending facility rate | 5,00% | 6,25% |
| Change over the quarter | Decrease (-25 bps) | Stable (no meeting in Q1) |
| Growth in 2025 (latest available data) | 6,7% | 3,5% |
| Growth forecast 2026 (latest available data) | 6,4% | 2,9% |
| 2026 Inflation Forecast | 1,4% | 2,3% |
Country focus and key players
IV.1Mali
Mali's electricity system remains heavily reliant on imported fuels and infrastructure failures. For reference, a 2020 UNDP study estimated the generation mix at approximately 69% thermal, 26,8% hydroelectric, and 4,2% solar. Since 2025, the JNIM blockade and insecurity along several corridors have regularly disrupted Bamako's fuel supply. After an improvement starting in December 2025, the diesel shortage worsened again in March 2026. At the same time, a fire at the SEMAF substation in Sébénicoro on the night of February 23-24 damaged critical network equipment. By mid-March, some neighborhoods were experiencing more than 24 consecutive hours without electricity, while others had only three to seven hours of service per day, whereas a target of approximately 19 hours had been announced before Ramadan.1
IV.2Regional (Guinea / Mali)
The Fomi Dam, located on the Niandan River in Upper Guinea, is a multi-use project combining hydroelectric power generation and irrigation. Available preparatory documents generally indicate a capacity of approximately 90 MW and highlight its downstream transboundary impacts, particularly on the irrigated areas of the Office du Niger in Mali. On January 14, 2026, a strategic meeting in Conakry brought together Guinean officials and the Chinese ambassador to discuss reviving the project; on February 20, the Guinean Ministry of Planning indicated its intention to move the project from the discussion phase to implementation. At the time of writing, however, no verified information was available to confirm that financing had been finalized or that work had actually resumed.3
T1 events and contextual markers
Mali: Fuel blockade disrupts supply corridors
Insecurity and the blockade imposed by JNIM reduce the arrival of fuel to Bamako and contribute to tensions on electricity and transport.
Logistics vulnerabilityMali: Partial improvement in supply
The resumption of escorted convoys provides a respite on the supply of Bamako, without resolving the structural causes of the crisis.
Temporary improvementBEAC: the TIAO is raised to 4,75%
The decision taken in December sets the level of the key interest rate which remains in effect throughout the first quarter of 2026.
TIAO: 4,75%Guinea: Strategic meeting on the revival of Fomi
Guinean authorities and the Chinese ambassador are examining the modalities for restarting the multi-purpose dam.
Historical project: ~90 MWSenegal: Four shipments of Sangomar oil sold
The official January report states that four shipments represented approximately 3,8 million barrels of traded oil.
3,8 million bottles soldGuinea: Fomi is presented as entering a recovery phase
The Ministry of Planning indicates that it wants to move the discussion process into an implementation phase, without announcing at this stage that funding is definitively secured.
Relaunch, not yet financial closureMali: Fire at the SEMAF post in Sébénicoro
A fire damages equipment at the station and contributes to the degradation of Bamako's power supply before the new diesel shortage in March.
Major network incidentBCEAO: cut in the key interest rate
The main policy rate is reduced from 3,25% to 3,00% and the marginal lending facility rate from 5,25% to 5,00%, effective March 16.
-25 bpsMali: Diesel shortages compound severe power outages
The available diesel is primarily directed towards EDM; several districts report very short supply times and sometimes more than 24 consecutive hours without electricity.
3–7 hours/day in several areasSenegal: Sangomar maintains high sales volumes
Three shipments representing approximately 2,98 million barrels were traded in March, according to official data.
2,98 million bottles soldBEAC: Rates to be maintained confirmed
The first regular session of the Monetary Policy Committee in 2026 maintains the TIAO at 4,75% and the marginal lending facility at 6,25%.
4,75% · 6,25%GTA: Kosmos confirms a T1 rating higher than nominal capacity
Kosmos reports annualized gross production equivalent to approximately 2,85 Mtpa of LNG and 9,5 gross cargoes for the quarter, above the nominal 2,7 Mtpa.
2,85 Mtpa · 9,5 cargoesAnalysis
Taken together, the events of the quarter reveal less of a single regional trajectory than three distinct forms of vulnerability or transition. In Mali, the March crisis cannot be attributed to a single cause: the diesel shortage compounded a significant incident on the electricity grid, in a system historically heavily reliant on thermal power. In Senegal, the situation is different: hydrocarbon production is progressing, but domestic value creation now depends on the completion of gas transmission and onshore power generation infrastructure. In Guinea, Fomi notes that significant hydroelectric potential only becomes usable capacity after the completion of financial, contractual, environmental, and operational milestones that were still pending in Q1.
None of these three trajectories is complete by the end of the quarter. Mali remains vulnerable both to the security of its logistics corridors and the resilience of its network. In Senegal, gas-to-power projects are still under construction or in the planning stages. In Guinea, the relaunch of Fomi is a political and technical signal, but not yet proof of a funded and completed project. The common thread, therefore, is less the completion of major projects than the testing of each country's capacity to reduce an identifiable structural dependency.
Perspectives and points to follow
In Mali, the central issue is twofold: ensuring a sustainable fuel supply and the network's capacity to absorb or circumvent major technical incidents. In Senegal, the challenge lies in converting the now significant hydrocarbon production into domestic energy availability. In Guinea, the tipping point will be the transition from a diplomatic and technical revival of the Fomi project to documented financing and subsequent implementation.
In Mali, corridor security, convoy frequency, diesel availability for EDM (Électricité de Mali), and the upgrading of electricity transmission infrastructure will be crucial. In Senegal, the timeline for the gas connection to the Saint-Louis/Gandon area and the progress of the onshore power plant will be the main indicators. In Guinea, the announcement of firm financing, an implementation contract, and a work schedule for Fomi will distinguish a genuine relaunch from a new preparatory phase.
The evolution of the cuts and diesel supply in Bamako; the official monthly reports on Sangomar and GTA; documented announcements on the gas connection and the Saint-Louis/Gandon power plant; as well as any financing agreement or work schedule concerning Fomi.
A simultaneous and sustained improvement in logistical security and network resilience in Mali would significantly alter the interpretation of the crisis. In Senegal, a substantial delay to the pipeline or power plant would postpone the realization of the expected domestic benefits from gas. In Guinea, financial closure and physical start-up of Fomi would constitute the clearest signal of a phase change for the project.
For Sahel countries that remain dependent on imported fuels, energy resilience depends as much on logistics and security as on installed capacity. For new hydrocarbon producers, the challenge is to quickly connect exports to domestic uses. For major regional hydroelectric projects, the quality of financing and execution remains as crucial as the projected technical potential.
| Path | Evaluation | Conditions |
|---|---|---|
| Progressive diversification | Central scenario | The fuel situation in Mali is partially stabilizing thanks to the continued escorted convoys, even without a complete resolution; Senegal's domestic gas infrastructure is progressing towards the mid-2026 target; Guinea is securing preliminary financing conditions for FOMI in 2026. |
| Uneven progress | plausible | The Malian crisis continues to alternate between relapses and partial improvements without a lasting resolution; the timetable for the Saint-Louis power plant is falling behind schedule; discussions on Fomi continue without a conclusion of funding in 2026. |
| Further deterioration | Risk scenario | The blockade in Mali is intensifying and worsening the electricity crisis beyond what was observed in the first quarter of 2026; security or financial difficulties are blocking the development of Senegal's domestic gas infrastructure or the revival of Fomi. |
Analysis Africa Signal
This edition primarily highlights the difference between having an energy resource and having a resilient energy system. In Mali, the March crisis combined a diesel supply constraint with a fragile grid: it demonstrates that energy security depends on several links simultaneously. In Senegal, Sangomar and GTA confirm the ramp-up of production, but the next decisive step lies onshore, in the infrastructure capable of converting gas into domestic electricity. In Guinea, Fomi illustrates the opposite case: the hydroelectric potential has been known for a long time, but the project's economic value still depends on the ability to translate political impetus into financing, contracts, and construction. The central theme of the quarter is therefore execution: securing flows, strengthening networks, and converting announced projects into actually available capacity.
Sources and references
- 1.Deutsche Welle, "Mali: Power cuts intensify during Ramadan", March 9, 2026; Africa Center for Strategic Studies, Press review of March 11, 2026, on the diesel shortage and the priority given to EDM; allAfrica, “Mali: Bamako is experiencing a shortage of diesel fuel and severe power and water cuts”March 16, 2026; Journal du Mali, edition from March 5 to 11, 2026, on the fire at the SEMAF substation in Sébénicoro; UNDP, reference study on the Malian electricity mix in 2020.
- 2.Ministry of Energy, Petroleum and Mines of Senegal, Monthly production and marketing reports from Sangomar and GTAJanuary-March 2026; Kosmos Energy, First quarter 2026 resultsMay 6, 2026, at an annualized rate of 2,85 Mtpa, the 9,5 cargoes and domestic infrastructure; APS, “Phase 1 GTA: 20 to 25% of LNG production directed towards the domestic market”, May 23, 2025, for the medium-term public objective.
- 3.Ministry of Planning, International Cooperation and Development (Guinea), "FOMI Dam: Towards the effective launch of a strategic project"February 20, 2026; African Development Bank, Fomi multi-purpose dam project preparation documents ; World Bank, project preparation documents on transboundary effects and downstream irrigation.
- 4.BCEAO Communiqué from the meeting of the Monetary Policy Committee of 4 March 2026 BEAC press releases from the Monetary Policy Committee, in particular the decisions of December 2025 and April 2, 2026.
